Project: rlinks
This document tracks major project phases, their objectives, and completion status.
Each phase has:
- Objective: What we're trying to achieve
- Key Results: Measurable outcomes
- Status: Planning → Active → Complete
- Duration: Actual time spent
Status: ✅ Complete Duration: Initial inception Objective: Define the problem space and architectural approach
- ✅ Threat model documented (
docs/security.md) - ✅ Core principles established (
docs/GUIDELINES.md) - ✅ Schema designed (
docs/schema.md) - ✅ High-level architecture defined (
docs/architecture.md)
Status: ✅ Complete Duration: Early development Objective: Validate approach with working proof-of-concept
- ✅ rlinks-core library with data structures and validation
- ✅ rlinks-cli with basic CRUD operations
- ✅ rlinks-worker with redirect resolution
- ✅ Unit tests passing across all crates
- ✅ Basic CI/CD setup
Status: 🔄 Active (Started 2026-01-28) Objective: Complete specification and establish comprehensive testing
- 🔄
docs/SPEC.mdfinalized (80% complete) - ⏳ Integration test suite established
- ⏳ E2E test scenarios defined and passing
- ⏳ Performance benchmarks baseline captured
- Consolidate reserved codes (T1)
- Define error response formats (T3)
- Formalize schema migrations (T4)
- Specify CLI commands in detail (T5)
- Document integration points (T6)
Status: ⏳ Planning Objective: Deploy to production with monitoring and limited usage
- Terraform infrastructure deployed
- Worker deployed to Cloudflare
- Monitoring and alerting active
- Basic redirects operational
- Incident response procedures tested
Status: ⏳ Future Objective: Stabilize for public use
- Public documentation complete
- Analytics dashboard operational
- Performance validated under load
- Security audit completed
- Migration tooling tested
Status: ⏳ Future Objective: Full production readiness
- SLA defined and met
- Backup/recovery procedures validated
- API versioning strategy implemented
- User onboarding streamlined
Legend:
- ✅ Complete
- 🔄 Active
- ⏳ Not started
- 🚫 Blocked
Update Rule: Update phase status when key results change significantly or when transitioning between phases.